$1.4bn SMForward Program at Sacramento International Airport Advances with Major Upgrades Underway

by Justin @TradesBuilt
13 May 2026
in Projects
0
SMForward Program at Sacramento International Airport
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter


Implementation of the $1.4bn SMForward program at the Sacramento International Airport advances with major upgrades underway. The project is gearing up for a busy summer as the travel season promises to be eventful. With Memorial Day less than two weeks away, the airport is set of another busy summer travel season. Moreover, the World Cup is nearing as the U.S. prepares major infrastructural facilities to host people from all over the world.

The Sacramento International is no different as there are several major improvement projects across the airport. These include ongoing construction work on the new pedestrian bridge at Terminal B and the airport’s new 5,5000-space parking garage.

Airport officials said both projects remain on track to be completed by the end of the year. However, neither is expected to open before the summer travel rush begins. SMF said last summer was the busiest summer travel season on record. Nonetheless, officials project passenger numbers could surpass that mark again this year. Another major airport expansion is also taking place at the Austin Bergstrom International Airport in Texas after securing a $1.18bn financing package.

The airport successfully completed an Airport System Revenue Bond sale that saw it secure the much needed funding. The transaction marks the largest bond sale in the history of  the airport and the City of Austin. The funds will support near-term projects within the Airport Expansion and Development Program (AEDP).

Outlook on the SMForward Program at Sacramento International Airport

The SMForward program at the Sacramento International Airport is bringing with it various changes to the airport. Among some of the changes travelers will notice this summer are new restaurants opening in Terminals A and B, along with upgrades already in use inside the existing parking garage. “One of our biggest improvements since the last summer is that our parking garage now has a parking guidance system that’s the red and green lights that direct you to a spot that’s open, so you don’t have to circle,” said Lindsay Myers, Sacramento International Airport spokesperson.

The parking guidance system uses red and green lights above parking spaces to help drivers quickly identify available spots. Airport officials are also encouraging travelers planning to park in the garage this summer to arrive before 7 a.m. They note this is because the garage typically reaches capacity on busy travel days, though other parking lots remain open. Some travelers at the airport Monday morning said they welcomed the ongoing improvements.

“It’s awesome, it’s really amazing. I think it’ll make travel a little bit easier for everyone else. It makes it easy too. From checking in to everything, it makes it easier,” said travelers Randy Stephens and Jan Stephens. Over the next several years, additional projects are also planned at SMF, including an expansion of Concourse B, a new Terminal A exit road and a consolidated rental.

SMForward Program at Sacramento International Airport
Implementation of the $1.4bn SMForward program at the Sacramento International Airport advances with major upgrades underway.

Project Factsheet:

  • Project Name: SMForward Program
  • Location: Sacramento International Airport, California, USA
  • Estimated Investment Value: $1.4 Billion
  • Project Type: Airport Expansion and Modernization Program

Timeline

  • 2026: Major upgrades actively under construction
  • Summer 2026: Peak travel season preparations underway
  • End of 2026: Expected completion of pedestrian bridge and new parking garage
  • Future Phases: Additional terminal and roadway expansions planned over coming years

Site & Scale

  • Airport: Sacramento International Airport (SMF)
  • New Parking Garage Capacity: 5,500 spaces
  • Major Facilities Under Construction
  • New pedestrian bridge at Terminal B

Multi-level parking garage

  • Future Expansions:
  • Concourse B expansion
  • New Terminal A exit road
  • Consolidated rental car facility

Project Teams

  • Project Owner: Sacramento International Airport (SMF)
  • Airport Authority: Sacramento County Airport System
  • Airport Spokesperson: Lindsay Myers

Infrastructure Scope

  • Construction of new pedestrian bridge connecting Terminal B
  • Development of 5,500-space parking garage
  • Installation of smart parking guidance system with red/green indicators
  • Terminal restaurant and concession upgrades
  • Future expansion of Concourse B facilities
  • Roadway and traffic circulation improvements
  • Future consolidated rental car infrastructure

Strategic Objectives

  • Improve passenger movement and airport accessibility
  • Increase parking and terminal capacity ahead of growing passenger demand
  • Prepare airport infrastructure for increased tourism and World Cup-related travel
  • Enhance traveler experience and operational efficiency
  • Support long-term regional air traffic growth

Challenges

  • Managing construction during active airport operations
  • Handling expected record-breaking summer passenger volumes
  • Parking congestion during peak travel periods
  • Ensuring projects remain on schedule before future global travel events
  • Coordinating phased infrastructure upgrades across multiple airport areas

Current Status

  • Major construction activities actively underway
  • Pedestrian bridge and parking garage remain on track for completion by end of 2026
  • New parking guidance system already operational
  • New restaurants opening in Terminals A and B
  • Airport preparing for another record summer travel season
Tags: Construction NewsProjectsUpcoming Construction Projects
Justin @TradesBuilt

Justin @TradesBuilt

Next Post
Ground Broken on $200 Million Hospital Expansion in Newport News

Ground Broken on $200 Million Hospital Expansion in Newport News

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Recent Posts

  • Ground Broken on $200 Million Hospital Expansion in Newport News
  • $1.4bn SMForward Program at Sacramento International Airport Advances with Major Upgrades Underway
  • $6bn Abu Dhabi Solar Project: JinkoSolar Signs 2GW PV Module Deal for Masdar RTC Energy Project
  • $7bn Gia Binh International Airport Construction in Vietnam Advances With DAA Partnership
  • Dammam Copper Plant: $566m Chinese-Saudi Joint Venture Drives Saudi Industrial Construction Boom

Recent Comments

No comments to show.

Archives

  • May 2026
  • April 2026
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023

Categories

  • Economy & Labor
  • News
  • Projects
  • Safety
  • Economy & Labor
  • Home
  • Projects
  • Safety
  • Sample Page

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Economy & Labor
  • Home
  • Projects
  • Safety
  • Sample Page

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.