$165bn Project Jupiter Data Center by Oracle to Utilize Bloom Energy Fuel Cells to Power Campus

by Justin @TradesBuilt
28 April 2026
in Projects
0
Project Jupiter Data Center by Oracle
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter


The $165bn Project Jupiter data center by Oracle is set to utilize Bloom Energy fuel cells to power the campus. The new development on the campus in Doña Ana County, New Mexico was announced by Oracle and BorderPlex Digital Assets. Furthermore, it is part of Oracle and Bloom’s previously announced expanded partnership. It will be supported by up to 2.45 GW of installed Bloom fuel cell capacity.

This updated power design will replace Project Jupiter’s previously planned gas turbines and diesel generators. Moreover, it will consolidate the facility into one single microgrid campus.

Fuel cells are a more optimal option as they generate electricity without combustion. Through this, the Bloom microgrid is highly efficient with low emissions and water use. Compared to its previously planned gas turbines, Project Jupiter with the Bloom microgrid will reduce emissions by approximately 92%. Furthermore, it will use a negligible amount of water. Despite advancements in making sure data centers are accountable for the resources used, grids are still facing challenges. For instance, Texas state-owned grid operator ERCOT is facing challenges as it seeks to adjust and accommodate data centers to an already saturated grid.

Scope of Implementation on the Project Jupiter Data Center by Oracle

Mahesh Thiagarajan, executive vice president, Oracle Cloud Infrastructure, noted his excitement on latest Project Jupiter data center. We are excited to move forward with this updated energy solution, which reflects our commitment to both the latest innovation and community priorities as we advance the next generation of AI infrastructure,” he noted. Furthermore, he added “Bloom’s fuel cell technology enables us to deliver highly reliable on-site power with a lower environmental footprint—supporting the project’s performance needs while contributing to stronger environmental outcomes.”

BorderPlex will continue supporting Project Jupiter’s success in New Mexico while advancing additional growth infrastructure opportunities. It will also advance other clean energy initiatives that expand initiatives in the state and beyond. Oracle will continue to bear all energy costs for Project Jupiter, ensuring the initiative has no impact on residents’ electricity rates or grid stability.

Furthermore, the data center’s closed-loop, non-evaporating cooling systems designed to minimize day-to-day water use. Construction continues to move forward on schedule. Over the life of the project, Oracle expects Project Jupiter to create 4,000 construction jobs. It is also expected to support 1,500 ongoing positions on-site and in the surrounding community.

Project Jupiter Data Center by Oracle
The $165bn Project Jupiter data center by Oracle is set to utilize Bloom Energy fuel cells to power the campus

Project Overview

  • Project Name: Project Jupiter Data Center
  • Project Type: Hyperscale AI data center campus
  • Value: ~$165 billion
  • Power Capacity: Up to 2.45 GW (fuel cells)
  • Purpose: Next-generation AI and cloud infrastructure
  • Status: Under development; construction ongoing

Key Stakeholders

  • Developer / Operator: Oracle
  • Energy Partner: Bloom Energy
  • Development Partner: BorderPlex Digital Assets
  • Key Figure: Mahesh Thiagarajan

Location

  • Site: Doña Ana County
  • State: New Mexico
  • Country: United States

Scope

  • Large-scale AI data center campus
  • On-site microgrid powered by fuel cells
  • Closed-loop cooling system with minimal water use

Funding / Delivery Model

  • Privately funded by Oracle
  • Integrated energy solution via Bloom partnership
  • Developer-led delivery with on-site power generation

Status

  • Construction progressing
  • Energy design updated (fuel cells replacing turbines)
  • Microgrid integration underway

Key Risks & Challenges

  • Large-scale energy infrastructure integration
  • High capital intensity
  • Coordination of advanced power and cooling systems

Strategic Significance

  • One of the largest data center projects globally
  • Major shift to fuel cell-powered infrastructure
  • Supports expansion of AI computing capacity

Sustainability Features

  • 92% emissions reduction vs. prior design
  • Minimal water consumption
  • Non-combustion energy generation

Economic Impact

  • 4,000 construction jobs
  • 1,500 permanent jobs
  • No impact on local electricity rates
Tags: Construction NewsProjectsUpcoming Construction Projects
Justin @TradesBuilt

Justin @TradesBuilt

Next Post
Commonwealth as a First Fusion Energy Company

PJM Connection Application Placed for First Fusion Energy Commercial Power Plant by Commonwealth

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Recent Posts

  • $15 Billion Google AI Infrastructure Project Accelerates India’s National Digital Buildout
  • PJM Connection Application Placed for First Fusion Energy Commercial Power Plant by Commonwealth
  • $165bn Project Jupiter Data Center by Oracle to Utilize Bloom Energy Fuel Cells to Power Campus
  • $8 Billion Nordic Data Center Project: Kitebrook Infra Launches 500MW Data Center Venture in Norway
  • $700 Million Soda Mountain Solar and Battery Storage Project Appoved by California

Recent Comments

No comments to show.

Archives

  • April 2026
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023

Categories

  • Economy & Labor
  • News
  • Projects
  • Safety
  • Economy & Labor
  • Home
  • Projects
  • Safety
  • Sample Page

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Economy & Labor
  • Home
  • Projects
  • Safety
  • Sample Page

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.